Up until now we always followed the philosophy of summing up resource planned efforts to task level, but not rolling down planned effort from the task to its resources. This caused confusion because clients were editing planned effort at task level in the task list and it was not updating the resource planned effort. Now we also roll down planned effort from task to resource if there is only one resource assigned to the task. If the task has more than one resource you need to open the task details RESOURCES tab and edit planned efforts for each resource